Can a variable be used (say equipment id) in a PM Activity task plan? The reason I ask is because each piece of equipment has a different checklist and I think only 1 task plan with checklist is recognized per PM. Instead of having multiple PMs for the different task plans, I am wondering if I can pass a variable of the equipment id to the correct task plan for that equipment. So the equipment ID would be in the task plan code. I hope that makes sense. It may just be easier to have multiple PMs.
Actually, I think I may be able to do this with Checklist Filters.