Hello,


I am curious on how to possibly setup a work order that requires doing 3 reading over a weekly period. I thought I could utilize the reoccurring checklist option on a task plan checklist, but it appears that this is not allowed. I really do not want to create 3 separate WO's for a week. Anyone possibly run into this scenario and figure out how to do this?


Thanks John

1 answer0 replies
0
1
jhobor
May 10

John - did you try the reoccurring Meter Reading on the task plant checklist? If that truly doesn't work what about still using the task plant checklist but instead labeling them as Meter Read #1, Meter Read #2, and so forth?